ORB performed platform design work and ladder installation design. Other structural designs included in this project are as follows:

Circulating Water Intake Structure

  • intake screen platform for cleaning debris from the screens
  • replacement of steel decking and access ladder to the discharge isolation valves

CT1 and CT2 Enclosure South Platform Ladders

  • installation of additional access ladders

HRSG 1 Main Steam Stop Valve Actuator Platform

  • extension of existing platform for improved actuator access

HRSG 2 Main Steam Stop Valve Actuator Platform

  • installation of new platform for improved actuator access

Fuel Oil Piping Crossovers

  • manufacture and installation of three piping crossovers

Location: Payne Creek Station, FL

Date

January 3, 2013

Client

Seminole Electric Cooperative, Inc.

Category

DESIGN