ORB performed platform design work and ladder installation design. Other structural designs included in this project are as follows:
- Circulating Water Intake Structure
- intake screen platform for cleaning debris from the screens
- replacement of steel decking and access ladder to the discharge isolation valves
- CT1 and CT2 Enclosure South Platform Ladders
- installation of additional access ladders
- HRSG 1 Main Steam Stop Valve Actuator Platform
- extension of existing platform for improved actuator access
- HRSG 2 Main Steam Stop Valve Actuator Platform
- installation of new platform for improved actuator access
- Fuel Oil Piping Crossovers
- manufacture and installation of three piping crossovers